49th Street and Alley Paving Program

49th Street and Alley Paving Project Updated 11/20/2026

Important Dates!

  • 49th Street
    • Asphalt paving complete.  Cooling down.  Can drive on after 5pm.
  • 48th/49th Street Alley
    • Asphalt paving complete.  Able to drive on.
  • 45th Street Alley
    • Asphalt paving being worked on currently.
  • Mitchell Street
    • Patching job being completed

All other improvements related to this current construction project are planned to be completed next spring.

Yard Waste: Do not place yard waste in the street.  It can be brown bagged in a yard waste type bag (Menards / Home Depot) and placed near regular trash container. 

Click here for a copy of the letter that was sent to residents

Check back for updates on alley reconstruction.

Any questions, please contact the Village Engineer, Ben High, at 262-317-3273

 

 

49th Street and Alley Paving Program