49th Street and Alley Paving Program

49th Street and Alley Paving Project Updated 11/04/2026

Important Dates!

  • 49th Street
    • Curb and gutter removals and concrete pavement removals to occur the week of November 2nd.
    • Concrete replacement will occur soon after the removals and will need need 5 days of curing prior to asphalt paving operations.
    • Potential asphalt paving to occur the week of November 16th.
  • 48th/49th Street Alley
    • Additional milling operations may occur the week of November 9th.
    • Potential asphalt paving to occur the week of November 16th.
  • 45th Street Alley
    • Concrete pavement removals to occur the week of November 2nd.
    • Potential asphalt paving to occur the week of November 16th.

All other improvements related to this current construction project are planned to be completed next spring.

Yard Waste: Do not place yard waste in the street.  It can be brown bagged in a yard waste type bag (Menards / Home Depot) and placed near regular trash container. 

Click here for a copy of the letter that was sent to residents

Check back for updates on alley reconstruction.

Any questions, please contact the Village Engineer, Ben High, at 262-317-3273

 

 