49th Street and Alley Paving Project Updated 11/04/2026
Important Dates!
- 49th Street
- Curb and gutter removals and concrete pavement removals to occur the week of November 2nd.
- Concrete replacement will occur soon after the removals and will need need 5 days of curing prior to asphalt paving operations.
- Potential asphalt paving to occur the week of November 16th.
- 48th/49th Street Alley
- Additional milling operations may occur the week of November 9th.
- Potential asphalt paving to occur the week of November 16th.
- 45th Street Alley
- Concrete pavement removals to occur the week of November 2nd.
- Potential asphalt paving to occur the week of November 16th.
All other improvements related to this current construction project are planned to be completed next spring.
Yard Waste: Do not place yard waste in the street. It can be brown bagged in a yard waste type bag (Menards / Home Depot) and placed near regular trash container.
Click here for a copy of the letter that was sent to residents
Check back for updates on alley reconstruction.
Any questions, please contact the Village Engineer, Ben High, at 262-317-3273 
49th Street and Alley Paving Program